Main phases of repair works in the apartment 83813
Main phases of repair works in the apartment.
How to start repair of the apartment?
The first stage of the repair work of old apartments is the destruction and taking apart first off of the worn out walls and partition walls, removing the wall and ceiling finish. This stage is one of the most "filthy" affordable top plumbing company phases of the repair work.
One more amongst the most important and "dirty" works is the window block replacement. It is necessary to do this firstly because dirt and dust will be unallowable during following phases and it is prohibited at all to open windows throughout painting and wallpaper works (big drops of the temperature and wetness are unallowable). After mounting windows and windowsills it is needed to load them instantly in polyethylene film and recommended best plumbing company to cover windowsills in addition by the fiber board (in order to prevent scratches).
The following stage is circuitry. Circuitry can be set up in walls or along the floor. Wiring is made inside the pipes to ensure electrical safety and boost dependability. The pipe protects electrical wiring from external damages and enables to replace the wire totally without breaking walls and flooring merely by placing the brand-new wire instead of the old one.
House Painting follows the electrical wiring. The regular mistake throughout the synchronised conducting of such works takes place when employees forget to set out among the cables and home painters have currently plastered and top-rated plumbing company smoothed out the wall. As an outcome, extra works are required to seal chases on the finished wall. The places of the feed switch and wall outlet area and their number must be thought-out in advance. The scheme of power circuitry is normally included into the design project.
Later on the system must be ready to service in case of failures. In addition to the wirings, the telephone cable television and the TV cable are laid out. The power cable should not be laid out near the telephone and antenna cables to prevent sound pickup and disturbance. The most peculiar minute is setting out the TV cable television. In order to make 2 (or 3) television set in the apartment the second cable television is typically simply "firmly soldered" in parallel, so the cable television resistance is reduced. As a result, the display quality is weakened, lots of programs can't be received and etc. In order to prevent such scenario it is needed to welcome a professional with unique equipment. He will determine the signal level of the each TV-feeder and set up TV-amplifiers or TV-filters.
Painting is the most long-term process, that is why it is performed all at once in all facilities, if it is possible. Hold-ups are related to the technology. Each applied layer of the plaster (or completing ending up) should dry completely before the work will continue.
Works in sanitary plans and the kitchen area begin at the same time with home painting. It is much better to meet so-called "dirty" works in the top place and simultaneously. In accordance with the plan of the sanitary service technician place welding, wall chasing and pipe run are conducted. Steam radiator admissions are prepared, taps and brackets are mounted, however radiators are not installed.
Then operates in sanitary arrangements are conducted according to the plan. The bath is installed, then walls are smoothed out and the tile is laid on walls. The list below stage is assembling ceiling and laying tiles on the flooring. And at last other hygienic devices, mixers and accessories are mounted.
After wiring, installation of rosette plates and terminal boxes the voltage is checked in all point. Ends of circuitry are insulated and set out into rosette plates. Sockets and breakers are not installed during this stage in order to save their surface look. The surface puttying of walls is carried out concurrently. The highly precise control of drying of the layer of the plaster (filling) is performed by drymeter. It is an unique instrument that determines moisture of the material.
The following phase is the process of fill. Fill can be made with different products-- from typical masonry cement-sand mixture to self-aligning floors. The advantage of the simple mixture is its cheapness, the disadvantage is that such mix is much harder aligned at the level and the final dry time of such fill is 40 days, only then the next stage of the deal with flooring can be carried out, i.e. the duration is too long. Self-leveling self-aligning floorings are a lot more pricey, but more technological. Lining up happens almost "immediately" i.e. fluid option of mix is poured out, then it runs and you receive the horizontal surface. The final dry time is 15 days i.e. you have significant time economy. The system "warm floor" is set up into the fill. If the so-called "wet procedures" are inapplicable the innovation of the dry lining up (the fill innovation) is utilized bases for floorings with adjustable flooring battens are mounted.
After fill door boxes and door are installed. Installation of doors must take into the account thickness of future floor covering. After setup the door can be removed its hinges and eliminated until completion of repair work or packed into polyethylene movie to protect from damages. All at once ceiling can be painted and the tile can be laid in that facilities where it was planned. The tile must be laid on the absolutely dry overlay.

Finishing of the flooring mounting depends upon the planned covering. For the most part (if surface covering is not the tile) fill is covered by bitumen mastic and plywood sheets are laid. They are repaired to the floor by self-tapping screws. One plywood sheet is fixed by 30-50 self-tapping screws to provide the close fixing of plywood and long-lasting service of the flooring without squeak and bulging. The plywood provides the additional heat- and acoustic insulation. After mounting of the plywood is completed, wallpaper for painting can be pasted on walls.
In properties where surface covering of the floor is laminated flooring or parquet hoard, the ordinary wallpapers are pasted (not for painting) in the very first place. Then the floor covering is mounted.
If surface covering of the floor is the block parquet, the parquet is laid top plumbing contractors in the first place, then it is scraped and covered by one layer of lacquer. After this the regular wall-papers are pasted and the parquet is covered by the rest layers of lacquer (depending upon the quality of the parquet and lacquer). The discussed repercussion is linked just with such rushing process when the terrific quantity of dust is produced. In spite of the reality that good floor grinders are geared up with the vacuum cleaner, the enough amount of dust is sped up on surrounding subjects consisting of walls. Dust is really acerbic and is severely washed off. That is why in order not to harm wallpapers, they are pasted after scrambling and in order the parquet do not take in the surplus wetness it is covered by the one layer of lacquer before wallpaper pasting.
After this the main works can be considered to be ended up. It is left just to install the plinths, ornamental aspects, breakers and sockets, drape holders, to hang doors, plant-bands and others.
In conclusion it is essential to note that the sequence of works was noted in general and can change depending on the guaranteed circumstance-- the number of spaces in facility, your resources, peculiarities of the building and construction of the multilevel premises. It is based upon common sense and every person capable of analysis can separately produce such a series.