Building your dream home part 63282
Building Your Dream Home-- Part 3
Exterior Framing Continues
With the homes sub-floor down and the exterior walls framed and up, the framing crew was on to the roof. Though the roofing system was rather basic in structure with simply a 12/12 pitch and no valleys it was a substantial framing endeavor due to just the size and height of it. Your home was 32 feet broad by 44 feet in length, and the exterior side walls stood 11 feet high in the fantastic space. This outside wall height of 11 feet translated into a roofing ridge that was 27 feet off the floor of the great room. As a result staging was needed to install the ridge pole and roofing rafters. In addition, considering that the period from the top of the walls to the ridge was so long, heavy 2x12s were needed for the roofing rafters. Within a week, however, the group had actually finished the installation of the roofing system rafters and your home started to take on real shape.
I should comment briefly about the sub-floor and outside walls before I move on.

I picked using tongue and groove plywood for the sub-flooring instead of OSB/particle board as I was concerned that the OSB was too sensitive to wetness. I was worried about this, both from the building and construction phase and from normal home usage. I was concerned that throughout the building and construction phase that snow and ice might possibly lead to damage such as warping. I have seen this before when OSB was utilized on sub-flooring. I was likewise worried that during the life of the home, that there could be water incidents, e.g. a leaking dishwashing machine or washer maker that likewise could likewise cause water damage to the flooring. I likewise believe that plywood is more powerful which it would attend to a more solid and rigid floor.
Regarding the exterior wall framing I utilized 2 × 6 construction. This is normal in New England as the extra wall depth enables greater insulation aspects; a must in chillier climates.
Sheathing the Outside of the Home
In order to get plumbing and electrical specialists onto a website generally they desire the home buttoned up. This includes the roofing system shingled and the doors and windows on. Hence my framing team moved onto the outside sheathing once the walls and roof framing were complete.
As with the sub-floor, I again chose plywood for the outside sheathing for the Dandenong plumbing experts exact same factors discussed previously. On the exterior walls outside grade plywood was utilized. On the roofing 5/8 exterior grade plywood was used. I understand many home builders today utilize OSB for both the walls and roofing, however, I still believe for more powerful building and construction plywood is the way to go.
The sheathing effort took about a week to complete. Throughout this time exterior windows and doors showed up on the website. Staging the delivery of product lowers theft and insurance threat along with keeps a less chaotic building and construction site. However, as I have actually shown earlier, communication is crucial when you are doing Just-in-Time material delivery.
Installing Exterior Doors and Windows
The installation of the doors and windows was a significant endeavor for this task as the lake side view of the home was actually a wall of windows; 32 feet in width and 27 feet in height. A lot of engineering had actually gone into the window design so that the 10 large customized windows would fit together like a jig saw puzzle. This said, when the windows arrived on website and were inspected, it was determined that some of them were not developed properly to the dimensions specified. After much argument with the framing team, the window supplier and me we reached a compromise on sharing the cost of repairing the windows. The window vendor took back the improperly sized windows and the framing crew began the setup of the doors and what windows they could set up. Fortunately the window vendor was able to go back to the site with the correctly sized windows within a few days and the building phase did not miss out on a beat.
Completing the Interior Framing
With the doors and windows set up, the framing crew proceeded to finish the Interior Framing. This was an interesting time, as the spaces began to take genuine shape. You could now stroll down hallways and into bedrooms and closet areas. Within just a few days the interior walls were total and the framing crew continued onto the roofing system for the shingling.
I should note that 2 × 4 building and construction was utilized on the interior walls as insulation was not needed on local plumber services the interior walls.
Shingling the Roof
The last task to complete before your home might be categorized as Buttoned Up was to install the shingles on the roof. Fortunately my framing crew was likewise able to do this task, thus eliminating the need for yet another subcontractor.
I chose a thirty years architectural shingle due to the quality and look I was attempting to attain on the home.
Though fairly an easy roofing, it was quite large and the weather was less than hospitable. As a result it took almost 2 weeks to finish this task. However, with the roofing system complete, my electrical and plumbing contractors were now able to start their work.
Also, with the main home 24/7 emergency plumber now structurally complete, the framing crew moved onto the garage framing and building phase. As an outcome of staging the garage behind the primary home construction stage, I was able to have subcontractors operate in parallel without getting in each others way.
Rough Electric and Plumbing
With the house Buttoned-Up, my Electric and Plumbing subcontractors appeared to start the roughing in stage of their particular tasks.
Rough Electric
I had actually satisfied a few days before on website with the Electric subcontractor to talk about the positioning of all the wall outlets and switches, as well as where the lights would be located. During our discussion he marked the wall studs for the positionings of the electrical electrical wiring boxes so that we could imagine the entire electrical wiring scheme. We likewise marked where the telephone and cable boxes would reside.
During the electrical rough in electrical wiring stage, the electrical contractor installed all the electrical wiring boxes and ran wire from the boxes to where the main circuit panel box would reside.
Rough Plumbing
As with the Electrical Subcontractor, I had actually fulfilled numerous weeks earlier with the Plumbing Professional. Throughout this meeting we talked about the kind of heat for the home, along with where the restrooms and kitchen area were to reside in the home. We also talked about kinds of restroom fixtures consisting of tubs, sinks and toilets. Consequently, when he showed up on site he brand-new exactly where to run main drain and supply pipes and vent stacks. He also roughed in all of the pipes for each bathroom and kitchen area pipes fixture.
Within a week both the Electrical and Rough Plumbing professionals had finished their tasks and had effectively passed their particular examinations.