ADU Project Contractor Contracts: Payment Schedules and Milestones
Accessory residence models appear small from the decrease, but they are real development tasks underneath the epidermis: utilities, foundations, framing, inspections, substitute orders, and dozens of humans moving in collection. The settlement you signal together with your ADU venture contractor makes a decision how that series receives paid for and who incorporates which hazards. Get the fee schedule and milestones right, and your price range tracks your growth. Get them improper, and you will be out of coins even as ready on drywall, or your contractor could possibly be carrying materials debt when a town inspection drags on.
I even have controlled and reviewed ADU contracts starting from modest storage conversions to at least one,2 hundred-rectangular-foot detached instruments with new utilities and solar. The styles are consistent, and the pitfalls repeat. Below is the playbook I want every owner of a house had earlier than they seek “ADU contractor close me,” elect an ADU builder from three rates, and signal the first template installed front of them.
The agreement shapes the construct, now not just the bill
When folk ask find out how to construct an ADU on my property with no complications, I tell them to recognition on two things: scope definition and the way funds flows towards progress. A crisp scope prevents “Oh, that wasn’t protected.” A balanced cost agenda prevents one get together from financing any other’s part of the process.
An ADU fashionable contractor strikes cash rapid. Permits and engineering are the front-loaded fees. Excavation and basis carry heavy materials and exertions early. Framing and rough-in hit subsequent. Finish trades, while obvious, are primarily a smaller slice than sitework and utilities. If your charge plan is to come back-loaded, the ADU contractor floats bills and will reduce corners or prioritize other jobs with greater money circulation. If it truly is too entrance-loaded, you carry the possibility of non-functionality. The perfect schedule aligns funds with milestones which might be objectively verifiable.
What a good milestone time table seems to be like
A smart accent residing unit builder will imply a milestone agenda that more or less fits the fee curve. I desire to see eight to twelve checkpoints on a flooring-up indifferent ADU, fewer on a garage conversion. The leading idea is discreet: pay for fee in position, now not grants. Each milestone ties to paintings you're able to look at or information one could cling, like allows for or signed inspection cards.
A fashionable pattern for a indifferent unit:
- Preconstruction and makes it possible for: deposit, design deliverables, allow submission
- Groundwork: demolition and hard grading, trenching, utilities, foundation
- Structure: framing, roof dried-in, home windows/doorways set
- Rough-in: mechanical, electrical, plumbing rough and linked inspections
- Insulation and drywall: close-in
- Exterior: siding, exterior trim, stucco or paint
- Interior finishes: cabinets, tile, flooring, trim, fixtures
- Final: punch listing, very last inspections, occupancy
The amounts can differ by using neighborhood and build category, however an affordable spread may beginning with 5 to 10 percent at agreement signing, then launch 10 to fifteen % chunks as milestones accomplished, with five to 10 percent retained unless final of completion and sign-off. If an ADU creation organization asks for 30 p.c down without a defined preconstruction deliverables, or desires such a lot of the fee until now inspections, question it. Rarely does that distribution align with accurate menace and settlement.
Choosing the money construction: fastened price, value-plus, or hybrid
Fixed charge suits so much house owners. You agree to a complete cost for a outlined scope. The ADU execs estimate risks and build designing an adu in California them into the number. Your payment agenda steps due to milestones, and amendment orders adjust the price solely whilst scope adjustments or unknown circumstances take place. The potential is predictability. The tradeoff is much less transparency into the contractor’s quotes, and also you pay for risk they priced in, however that chance doesn’t materialize.
Cost-plus shifts danger to you but offers transparency. You pay direct prices plus a price, frequently a proportion or a hard and fast management quantity. This can paintings if you choose high customization with a tradition ADU builder and settle for that the remaining expense is variable. It demands field: weekly payment stories, open books, and careful keep watch over of allowances. A hybrid mannequin sets a fixed value for popular work and a money-plus means for undefined factors, to illustrate, ancient sewer lateral substitute in a conversion wherein situations are unknown. For ADU layout and construct businesses, hybrids are time-honored because they possess equally design and building chance and can pivot as plans solidify.
For first-time ADU householders, I continually endorse a hard and fast fee with good-outlined allowances and unit fees for predictable unknowns, like rock excavation in line with cubic yard or subpanel upgrades at a suite value. Cost-plus is also truthful whilst industry rates are unstable, but solely should you get line-merchandise visibility and caps.
Deposits, mobilization, and preconstruction deliverables
You will see three early requests for money: a deposit to reserve scheduling, a layout check if the ADU contractor incorporates structure and engineering, and a mobilization payment for makes it possible for and undertaking setup. Tie each one to deliverables.
A prudent construction is a modest deposit, most of the time 5 percent, at signing to kick off layout. That buys proper paintings: site degree, initial plan set, and code evaluation. The next settlement should hit while the ADU clothier close to me promises allow-geared up drawings stamped by means of the engineer. Another cost can coincide with the let program submittal, satisfactory to quilt metropolis rates if the contractor is fronting them. I even have obvious property owners write tests quickly to the town or software for charges. It helps to keep accounting clear and eliminates any temptation to borrow from one assignment to fund an alternative.
If your ADU assignment contractor requests 20 percentage beforehand a unmarried drawing is produced, ask for a breakdown. Good ADU building products and services will coach a preconstruction time table with dates, outputs, and the gate for the subsequent price.
Aligning milestones with inspections you do now not control
Inspection timing is the so much overall resource of friction. On paper, “pay upon rough-in inspection pass” sounds clear. In certainty, it's possible you'll fail the primary time owing to a aspect, or the inspector won't display for two days, or a application necessities to approve the meter panel beforehand the building inspector will signal. None of this continuously suits interior a neat money calendar.
Solve it within the contract. Write that charge is due upon reaching the milestone or upon immense finishing touch of the milestone work able for inspection, with a holdback launched upon flow. For instance, unlock 80 percent of the framing milestone whilst the layout is complete and sheathed, then the ultimate 20 % as soon as the inspector indications. That split assists in keeping the team funded and preserves your leverage to get the inspection cleared.
ADU creation consultants who paintings cities weekly in most cases have a bead on inspection lead instances. Ask for his or her local timeline and component it into cash planning. In busy jurisdictions, difficult-in to insulation would possibly span per week longer than hoped.
Retention: the quiet software that protects equally sides
Retention is a small percent you dangle lower back from every single development charge. Many states set defaults for public works at 5 percent. In residential paintings, five to 10 p.c is traditional. It serves two reasons. It motivates the ADU homestead builder to handle punch record pieces quickly, and it affords you a cushion if human being disappears. That acknowledged, retention could be reasonable and not crippling. Releasing part of the retention at significant completion, then the the rest at ultimate inspection and lien releases, helps to keep things relocating.
I commonly layout retention on indoors finishes in another way than on sitework considering the ultimate 2 % of a venture can drag out: paint contact-ups, door modifications, a missing bathe trim ring. If you launch too much too quickly, you'll wait weeks whereas the most appropriate chippie finishes a top precedence job some other place. Retention maintains a small however significant incentive aligned along with your timeline.
Allowances and unit expenditures: the antidote to “TBD”
An allowance is a placeholder budget interior a fixed-fee settlement for one thing no longer but decided on, like tile or light furnishings. Without allowances, your alternate options are to stall your agreement except each end is picked or to hazard wide swings later. With them, you could sign and start layout and permitting at the same time as procuring finishes. The key's readability.
A indistinct “equipment allowance: $four,000” is simply not worthy. A important ADU construction issuer will list edition levels or a california adu statistics payment per merchandise: selection as much as $1,2 hundred, refrigerator as much as $1,600, washer/dryer up to $1,200. Same with floor: $four according to rectangular foot subject material installed as much as six hundred square ft, transitions and base blanketed. If you upgrade, you pay the distinction plus agreed markup. If you store, the credits should still move lower back. Insist on the markup expense in writing. Ten to 15 percent is regularly occurring on supplies for small residential paintings.
Unit bills deal with unknown field circumstances. If a sewer lateral wants replacement, the agreement can state $a hundred sixty five consistent with linear foot for 4-inch PVC to assets line, trench backfill, and pavement patch covered, or $300 per cubic yard for rock excavation if it's miles discovered. These numbers take away the guesswork and circumvent arguing in the dust.
Change orders: learn how to prevent them infrequent and manageable
Even the greatest accent living unit builder won't see because of concrete or behind a fifty-yr-outdated garage wall. Change orders appear. The trick is to outline the strategy and cost them enormously. A acceptable modification order involves an outline, intent, value breakdown, schedule have an impact on, and your written approval until now execution, with the exception of in emergencies affecting safeguard or climate insurance plan. For ADU reworking contractor tasks like conversions, I like a quick lane for minor variations under a threshold, say $1,000, to hinder time table delays, yet the whole lot nevertheless hits the paper path.
Watch for “design creep” written as container transformations. If you improve to a 12-foot slider overdue in framing, that isn't really a hidden circumstance, it's miles a scope difference. Expect genuine charges for reframing and a schedule hit for ordering. Good ADU gurus will provide you with a warning of downstream impacts. The most beneficial time to make colossal selections is all over design, not after trusses arrive.
Lien releases and who will get paid after you pay
You do not would like to pay two times for the similar paintings on the grounds that a subcontractor or seller information a lien. Protect your self with conditional and unconditional lien releases tied to every single cost. In many states, there are time-honored bureaucracy. A conditional release upon growth payment is brought with the bill. Upon cleared budget, the ADU contractor provides unconditional releases from themselves and substantial subs and providers for the covered era.
Ask how the ADU deploy companies supplier manages sub payments. Some homeowners decide on joint assessments to essential trades like the electrician or roof artisan. That process is clunky but mighty. A greater streamlined direction is to require facts of settlement downstream previously your subsequent milestone money. Trust is right, verification is better.

Insurance, bonding, and what occurs if a contractor disappears
Most residential ADU jobs will not be bonded. That is wide-spread. But your ADU task contractor should have usual legal responsibility and laborers’ compensation insurance. Ask for certificates that identify you as further insured for the mission handle. If they draw back, rethink. If you might be hiring an ADU layout and build organization that subs every part out, you favor to realize the ones subs are insured less than the enterprise’s coverage or raise their possess. This matters if a person receives harm digging your trench.
A efficiency bond is amazing for small ADUs and adds rate, yet for larger initiatives, say a 1,000-sq.-foot unit with California adu architectural design full sitework and keeping partitions, you can actually talk it. More simple is staged bills with retention and the habit of under no circumstances getting ahead of put in paintings. If an ADU contractor close to me closes their doors midway by, your retained dollars and unspent milestones are your defense web.
Permitting bills, utility charges, and who fronts them
Permit and utility bills vary wildly with the aid of urban and application district. I actually have noticeable let totals vary from a couple of thousand dollars for a undeniable conversion to extra than $20,000 for indifferent units with impression bills. Utility enhancements for electric carrier can run $three,000 to $7,000, from time to time a whole lot extra if trenching to a pole or transformer is required. Clarify inside the settlement who can pay those and when.
Many owners pay allow expenses straight away to the town and application after the ADU designer close me submits the software, with the contractor delivering a rate sheet as backup. That method avoids markups on flow-thru prices and helps to keep timing for your handle. If the ADU creation employer fronts these expenses, the milestone tied to “permit issued” needs to reimburse them, with receipts connected.
Scheduling milestones with seasonal reality
Concrete pours in January are slower. Exterior paint in rainy months can also push out. If you want a payment time table that minimizes friction, well known weather. Performance timelines can encompass weather day allowances. Payment triggers can enable partial releases while weather-touchy paintings is staged and capable, with the steadiness upon crowning glory at the subsequent dry window. I have published a element for roof dry-in hard work and ingredients added to the web page while a typhoon week hit, with snap shots and a tarp plan hooked up. That is superior than starving the team or risking a 0.5-equipped roof inside the rain.
Using a draw inspector or 0.33-occasion verifier
For owners who live out of the town or sense out of intensity, a draw inspector is an cheaper way to ascertain milestones sooner than repayments. A retired superintendent or a construction manager can talk over with, take photographs, and make sure that “difficult plumbing full” is not very three stub-outs and a promise. On a $250,000 ADU, spending several hundred bucks consistent with consult with reduces pressure for each person. Some lenders require this for structure loans. Even with cash tasks, it indicators to the ADU development consultants that your system is prepared, no longer antagonistic.
What the contractor necessities from you to maintain income go with the flow healthy
The first-rate ADU professionals hate chasing payments extra than they hate rain days. You can aid through surroundings one choice-maker, answering choices questions fast, and paying in the agreed timeline. Late repayments ripple by the schedule: subs decline to mobilize, subject matter deliveries slip, and your final touch date drifts. A contract that states price inside of 5 commercial days of milestone approval is reasonable. Consider putting one weekly status name for updates and approvals so no person waits on a faucet determination until the day beforehand rough-in.
Red flags in ADU charge schedules
Several patterns repeat inside the horror stories I had been called to unwind. If you notice these, sluggish down:
- Front-loaded deposit and mobilization totaling extra than 25 percent with no deliverables or city receipts
- Vague milestones like “difficult framing complete” without connection with inspection or dry-in
- No retention, or retention held simply at the stop other than frivolously throughout progress payments
- No allowances inspite of unfinished picks, or allowances so low they power a wave of high-priced alternate orders
- Refusal to give lien releases from subs or to disclose who the subs are
Two or 3 of those do no longer mean malice, yet they endorse inexperience or terrible programs. A professional ADU commonly used contractor has clean bureaucracy and does not take charge except work is accomplished.
How design and construct establishments must layout bills differently
When one firm owns architecture, engineering, and structure, they create more early expenditures and coordination initiatives. A intelligent ADU layout and construct agenda splits preconstruction into discrete deliverables: measured survey, schematic design, layout progression with choices, engineering, allow submittal, and allow approval. Each unlocks a money. Construction then follows the conventional milestone cadence.
Design time can balloon. To restrict procuring rounds of indecision, tie layout bills to a constrained quantity of revisions within scope, then hourly premiums beyond that. A just right accent residing unit builder will provide you with a decisions calendar so you prefer windows, outside finishes, and tile formerly the framers desire that archives. That calendar is as imperative because the price calendar.
Financing and the way lenders view milestones
If you might be applying a development mortgage or a residence equity line to fund your ADU, the lender most commonly requires a price range damaged into payment codes and draw requests tied to accomplished work. Often the lender’s draw inspector ought to assess progress in the past funds unlock. Align your settlement milestones with the lender’s different types. If your bank can pay only after a phase is total, plan for the contractor to bridge a brief gap or with a view to enhance and be reimbursed. Some ADU developers are install for lender attracts; many small operators should not and want a clean roadmap.
Also watch mortgage timelines. If the lender takes seven to ten days to fund a draw after inspection, positioned that into your fee phrases so the ADU contractor isn't very inadvertently floating two weeks of payroll.
Negotiating with no poisoning the relationship
Contracts set the guidelines, but initiatives are equipped with the aid of men and women. Approach negotiation as mutual risk management, not battle. The ADU contractor wishes predictable cash waft. You prefer predictable supply. Trade readability for trust. For illustration, conform to unencumber payment for windows when the order is positioned and also you see the enterprise affirmation and deposit receipt, with the balance for that line while windows are mounted and flashed. Contractors like this on account that window lead instances is usually eight to twelve weeks. You love it simply because your payment is attached to a proper order variety and schedule.
Offer brief approvals in substitute for particular documentation. Share your holiday or work travel calendar so disbursements usually are not delayed on account that you might be off-grid. These small courtesies keep crews for your web page in place of anybody else’s.
Garage conversions and the exceptional twists on milestones
Conversions behave differently. Structure is latest, however surprises lurk: unpermitted paintings in the ancient garage, sunken slabs that need topping, termite damage the place framing meets concrete, and capability panels that had been under no circumstances sized for an ADU. For these, I want milestones that isolate discovery early. After demolition and exposure, pause for a framing and slab contrast milestone. Price the figured out work as modification orders in opposition t unit fees wherein feasible. Only then continue into difficult-in.
Payment for utilities can be staged. You would launch cash when trenching and conduit are put in and inspected, even so whilst the panel improve is scheduled with the software, then a very last component when chronic is hot and inspected. That sequence continues momentum besides the fact that software scheduling takes longer.
The details that saves substantial headaches
Several clauses earn their save on each and every ADU:
- Weather and drive majeure: outline what counts, how days are tracked, and the way schedule and repayments adjust
- Dispute answer: mediation first, then arbitration or court docket, with venue certain; small tasks improvement from faster, much less formal paths
- Termination for trigger and convenience: what triggers it, treatment durations, and the way closing check is calculated
- Warranty and punch record: timelines for creating the checklist, completing it, and guaranty duration by approach; many ADU gurus give twelve months on workmanship, longer on corporation warranties
- Photography and placement get right of entry to: whether the ADU builder may additionally photo work for portfolio, and whilst it is easy to consult with appropriately devoid of disrupting crews
These are not gotchas, they may be obstacles. When equally events recognise the rules, the project breathes simpler.
A practical instance timeline with payments
Imagine a 750-sq.-foot indifferent ADU with a slab groundwork, hassle-free gable roof, and ordinary finishes. Total contract: $275,000, constant value, with allowances for home equipment and tile, and five percentage retention.
- 5 percentage at signing for design kickoff, paid upon receipt of schematic floor plan and code summary
- five % at let submittal with stamped structural drawings and vigour calcs, city value receipts provided
- 10 percentage at permit issuance and mobilization, fencing and layout on site
- 12 p.c. upon origin whole and inspected
- 12 % upon framing, roof dried-in, home windows set
- 12 p.c. upon rough-in MEP complete and inspections handed, eighty % released at immense of completion of hard-in, 20 percentage upon pass
- 10 % upon insulation and drywall hung and taped
- 8 % upon external end finished and painted
- 12 percent upon interior finishes installed: shelves, countertops, tile, doorways, trim
- 7 p.c upon great finishing touch and punch record issuance
- Retention: 2.5 p.c launched upon punch list crowning glory, 2.5 p.c upon very last inspection, COO, and unconditional lien releases
This cadence pays for work because it looks and maintains a significant quantity until eventually the closing five percent of projects are finished.
How to pick an ADU contractor who welcomes fair milestones
Ask for references from initiatives reminiscent of yours. Not simply pleased homeowners, however subs and providers. An ADU production brand that pays on time has subs who go back calls. Walk a recent task if that you can think of. You can be told much from a site: blank staging, labeled fabrics, up to date inspection playing cards, and a superintendent who understands what's coming the next day.
When you discuss terms, note the response. ADU production authorities who're positive will clarify their typical time table and adapt in which it makes experience. They will now not bristle at lien releases or documentation. They can have pattern invoices and a selections tracker. If a agency refuses not pricey retention or will not tutor a agenda of values for value-plus, stay browsing.
Final suggestions from the field
Most ADU tasks that pass sideways do no longer fail on craftsmanship. They fail on expectancies and money timing. A reasonable settlement reduces that threat via anchoring greenbacks to factual growth, through defining exchange order pathways, and via making every occasion’s tasks noticeable. Treat your price schedule like a activity agenda, because it is. It directs the circulation of labor as definitely because the serious path on a Gantt chart.
Whether you rent a boutique customized ADU builder for a jewel-field outdoor cottage or a larger ADU development corporation for a standardized plan, the comparable rules practice. Define milestones one can see and record. Set allowances that reflect your industry. Use retention correctly. Align with inspections without letting forms end the activity. Pay right away for validated work. Get releases. Keep communique weekly and fundamental.
Do this, and you deliver your ADU experts the runway to perform. More commonly than now not, you're going to cross a tenant or friend right into a properly-developed unit at the date you predicted, with a remaining settlement you are completely happy to make.